Aylesford Reservoirs

Emergency ground stabilisation, partial demolition and reconstruction of a strategically critical water reservoir asset.

The Aylesford Reservoir project incorporated the partial demolition and reconstruction of two reservoirs with a combined 20,000,000 litre capacity contained within reinforced concrete storage cells. Initial demolition works required extensive temporary works design and establishment, to ensure structural stability of the reservoir. The vast variety of site procedures included emergency remedial measures to the reservoirs such as over excavation of sink holes and making safe, investigation of sub slab voids and infilling with foamed concrete; achieving minimal delay to client operations, through early restoration of one reservoir.

These groundwork remediation works, undertaken in challenging, high risk conditions within live infrastructure and confined spaces, additionally incorporated ducting and drainage installation, compaction grouting, and engineered backfilling. The project was completed with reconstruction works to the reservoirs including concrete and steel element construction, followed by subsequent waterproofing of the structures and provision of new distribution infrastructure.

Location

Aylesford, Kent

Client

South East Water

Status

Complete

Duration

Service Used

Emergency Works, Ground Stabilisation, Demolition, Site Remediation, Structural Alterations, Groundworks, RC Structures, Contracting