Canterbury Prison Demolition

Start a Project

Demolition and enabling works at the former Canterbury prison

DDS Group delivered a turnkey solution at the former Canterbury prison site, facilitating the expansion of the neighbouring university. All divisions of DDS Group were employed throughout – from our groundworks services, to site remediation, to asbestos removal – to successfully complete the full scope in house.

Upon site possession, we carried out site establishment and asbestos removal, followed by demolition of numerous prison buildings, sections of the unlisted prison boundary wall and main accommodation block. A multitude of disturbance management strategies were enforced throughout the project; environmental monitoring stations were installed for dust, noise, and vibrations, ensuring levels did not exceed past agreed limits; communication channels were established and maintained, ensuring transparency between client, contractor, and stakeholders – including Canterbury Christ Church University.

Following successful completion of the demolition works, DDS Contracting secured the enabling package, incorporating extensive site remediation, following discovery of unidentified contaminants within the ground. The turnkey project was completed with installation of the contiguous pile retaining wall.

Location

Canterbury, Kent

Client

Canterbury Christ Church University

Status

Completed

Duration

13 weeks

Service Used

Asbestos Removal, Soft Strip, High Reach Demolition, Site Remediation, Enabling Works, Groundworks, Contracting