Demolition of 8no. mixed construction buildings, incorporating asbestos removal and site remediation.

DDS Group undertook the demolition of 8no. buildings of mixed construction; load bearing brickwork, steel frame, and reinforced concrete. A turnkey solution was delivered to the client, employing our in house demolition and asbestos removal services.

Prior to demolition commencement, isolations, soft strip works and asbestos removals were carried out – utilising designated building atriums as controlled drop zones. Structures were then demolished down to slab level employing high reach machinery, with the exception of the brickwork and steel exhauster building, which required mobile crane and hot cutting methods to remove the chimney and steel elements. Following demolition, slabs, foundations and hardstandings were broken out, and crushed arisings utilised to lay and compact a piling mat, as per client specifications.

Location

Fulham, London

Client

St William, Berkley Group

Status

Completed

Duration

16 weeks

Service Used

Asbestos Removal, Soft Strip, Demolition, High Reach Demolition, Site Remediation